1. Objective

Establish an executable contract for Open Knowledge Format v0.2 support before changing public APIs. This task is the dependency root for the other migration tasks.

Source of truth:

Do not rely solely on the current main: reproducible builds and tests must reference the pinned specification revision.

2. Version contract

Supported versions:

Resolution policy:

  1. An explicit supported okf_version in the root index.md sets the contract.
  2. Without a declaration, the effective version is 0.2, with the legacy fallbacks from §13 permitted.
  3. A v0.2 consumer reads an unknown declaration on a best-effort basis and preserves it as the declared version.
  4. An explicit API/CLI selector is an assertion. A conflict with the declaration must not silently change semantics.

The resolution model must distinguish:

The Go module, CLI binary, and plugin package versions are not okf_version.

3. Conformance matrix

Create a versioned matrix: spec clause → implementation → diagnostics → tests.

Hard [ERROR] diagnostics remain limited to §11:

Optional v0.2 field families do not become hard requirements:

The strict/policy layer checks malformed field families when present; they must not break permissive loading. Unknown keys/types/runtimes remain consumable.

4. Legacy contract

Support two fallbacks without implicit migration:

A legacy representation alone is not a conformance failure. Reading, fmt, index, and graph operations must not rewrite v0.1 documents.

Migration must be a separate preview/apply operation with an explicit actor and source mapping.

5. Ambiguity ledger

Record tooling policy decisions separately from the upstream specification:

Reflect each decision consistently in bundle, validator, CLI, MCP, fixtures, and documentation.

6. Canonical fixtures

Add one shared corpus:

Reuse fixtures in package tests, CLI/MCP E2E tests, and documentation snippets.

7. Deferred ABI

Explicitly exclude:

store.CommitReceipt is unrelated to executor.receipt.

8. Acceptance criteria

9. Dependency graph

Order:

  1. This task.
  2. bundle.
  3. In parallel: validator, graph, mutation engine, store guardrails.
  4. Mutation operations and migration.
  5. CLI and MCP.
  6. Skills/documentation and the final conformance gate across all interfaces.